Arnold Street Road Reconstruction and Upgrade
- Project categoryDrainage, Roads and carparks
- StatusCompleted
- Approx. start date07 February 2022
- Approx. end date30 June 2022
Council has completed works on Arnold Street.
The Federal Government has committed funding through the Roads to Recovery Program for the reconstruction and upgrade of Arnold Street, Ringwood.
The works will include:
- Construction of kerb and channel
- Pavement reconstruction and widening to 7.20 metres
- Vehicle crossing reconstruction
- Minor drainage upgrades
- Removal of the concrete threshold treatment at the Mullum Mullum Road intersection and replacement with an asphalt road pavement.
View the design plans
Arnold Street - detailed design plans(PDF, 6MB)
Further information
For further information on the proposed works, contact Council’s Project Engineer, Josh Dunstone on 9298 4454.
Contact details
Location
Arnold Street, Ringwood 3134 View map
-37.8042003,145.2344416
Arnold Street ,
Ringwood 3134
Arnold Street ,
Ringwood 3134
Arnold Street Road Reconstruction and Upgrade