Kubba Road footpath construction
- Project categoryFootpaths
- StatusPlanned
- Approx. start dateAugust 2025
- Approx. end date31 October 2025
In accordance with Council’s continuing commitment to the construction of footpaths within Maroondah to improve pedestrian access and safety, I can advise that funding has been made available in the 2025/26 financial year for the construction of a footpath on Kubba Road, Ringwood North.
The works will include:
- Construction of a new concrete footpath on the on the southern side of Kubba Road between 1 Kubba Road and Glenvale Road
- Construction of a new concrete footpath on the on the northern side of Kubba Road between Glenvale Road and Felix Crescent
- Construction of associated kerb ramp crossings at the Nicholas Court intersection
- Removal of one (1) tree and five (5) conifer bushes at the front of no. 3, 5 and 7 Kubba Road.
Tree Removal
The trees referenced above have been identified by Council’s Arborists for removal due to the trees’ existing conflicting alignment with the proposed footpath or the significant root systems that exist on the surface of the nature strip that will need to be removed to construct the footpath.
View the plans
Kubba Road footpath construction(PDF, 4MB)
Further information
For further information on the works, contact Council’s Engineering team on 03 9298 4357 or email maroondah@maroondah.vic.gov.au
Contact details
Location
Kubba Road, Ringwood North 3134 View map
-37.8014792,145.2167032
Kubba Road ,
Ringwood North 3134
Kubba Road ,
Ringwood North 3134
Kubba Road footpath construction