Lincoln Road footpath works

  • Project categoryFootpaths
  • StatusCompleted
  • Approx. start dateMay 2025
  • Approx. end date31 August 2025

As part of Council’s ongoing commitment to footpath construction and improvement work, Council has completed construction of the missing links of footpath and formalisation of the gravel path along Lincoln Road in Croydon. 

About the project

The works included:

  • Construction of a new concrete footpath on the northern side of Lincoln Road between Croydon Road and Arthur Place.
  • Construction of a new concrete footpath along the eastern side of Lincoln Road between Maroondah Hwy and Arthur Place.
  • Upgrade of the gravel path to a concrete footpath along the southern side of Lincoln between 6 Lincoln Road and Dorset Road.
  • Installation of twelve (12) new streetlights on existing service poles at various locations along the southern side of Lincoln Road and the section between Maroondah Hwy and Arthur Place.
  • Construction of three (3) new light poles between 70 Lincoln Road and Dorset Road.

The works also included the reconstruction of several vehicle crossings along the extent of works to allow the concrete footpath to extend through the vehicle crossing at compliant grades.

Council thanks the community for their patience and cooperation during these important upgrade works.

View the plans

Lincoln-Road-footpath-works-design-plans.pdf(PDF, 13MB)

Further information 

For further information on the works contact Council’s Engineering team on 1300 88 22 33 or email maroondah@maroondah.vic.gov.au

Contact details

Location

Lincoln Road, Croydon 3136  View map